Top

Case studies

Holt Sixth Form

Job details

Project Length – 14 Weeks
Completed on time
Contract Value: £500K – £750K
Completion Date: October 2016

The project

A difficult scheme due to tight access, limited working space around new building and a short programme. Construction of a modern 2 storey modular building with stylish overhang encapsulated into a historic school.

EvaBuild commissioned SI works to ascertain ground conditions to help design foundations and drainage options. Shallow strips and pads were found to be feasible. No local gravity FW connection available therefore extensive drainage including a foul pumping chamber was installed to service the new building.

Brickwork carried out by EvaBuild including scaffold package.

Hard landscaped areas of paving with raised planters and box hedging completes the package.

Client feedback

“A really good job from EvaBuild, even with all the extra work they still finished to programme. Compliments received by both school and architects.”

 

Contact EvaBuild

St Davids House, New Road, Newtown, Powys, SY16 1RB
Telephone 01686 623809   Email info@evabuild.co.uk

Linkedin

* indicates a required field